A joint venture (JV) of Talgo and Systra has secured a $138.9m contract from the Southern California Regional Rail Authority (SCRRA) in the US to rebuild up to 121 Bombardier passenger rail cars.

The JV has received a base order to overhaul 50 cars, while the contract for the remaining 71 cars is subject to availability of funds.

The scope of works on the Bombardier passenger rail cars encompasses a variety of upgrades to improve their overall reliability and performance of the fleet.

It includes modernising control voltage and battery system, lighting, passenger communication system and replacing the HVAC systems.

“Our joint venture is confident that the unique combination of experience and capabilities will provide the best value and most reliable on-time performance.”

Additionally, the Talgo-Systra JV will upgrade door operators and controls, remodel restrooms, provide new seat cushions, install floor covering and repaint the exterior.

All overhauling works will be carried out at Talgo’s facilities in Milwaukee.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Talgo president and CEO Antonio Perez said: “Our joint venture is confident that the unique combination of experience and capabilities will provide the best value and most reliable on-time performance on this Rebuild Project.”

The deliveries of the first cars are scheduled to begin 450 days following the notice to proceed.

Remaining units will be delivered in batches of five every 90 days, with the 50th car expected to be supplied in April 2023.

The Bombardier rail fleet is operated by SCRRA’s Metrolink, a commuter rail system in Southern California.